Reserve Studies

Foundation Forensics

Crack in a foundationCracks in foundations are by far the most common structural complaint raised in either reserve fund studies or transition studies.   They can occur in the youngest or newest condo building. As condo documents usually assign the maintenance responsibility of their repair to the association, board members and property managers take them very seriously.  Missouri condo buildings have many types of foundations including concrete block; brick; and mortared stone with the most common being poured concrete.

Most basements and garages have 4 to 6 inch concrete slabs and unless this is a slab-on-grade foundation, the slabs were poured independently of the foundation walls.  They are said to be ‘floating’.  Often the construction joint between the slab and wall can easily be seen.  The common slab crack complaint is hairline cracks appearing in spider web-like patterns.  These cracks can show up shortly after construction and are normally caused by shrinkage during the curing process.  The key point here is this type of slab cracking is rarely a structural problem, for after all, the slab could be completely removed leaving a dirt floor while the foundation walls and columns with footings will easily maintain a stable building.

Therefore, slab cracking is often more of a cosmetic problem.  Cracks are often repaired with a variety of grout, caulk, or epoxy products primarily to prevent groundwater penetration, insect entry, or radon gas infiltration.  Cracks showing differential movement on opposing surfaces can be a tripping hazard but more importantly an indication of serious sub-surface conditions needing further investigation.

Regarding foundation walls, the most typical problem with concrete walls are vertical hairline cracks, often starting at the top of the wall and traveling down to the floor slab.  A sub-set of these types of cracks are those that propagate often in a diagonal direction from stress concentration points such as the bottom corners of basement window openings.  The key point to remember is these types of cracks, even when they penetrate the entire thickness of the wall, normally do not constitute a structural problem as the loads from above pass unobstructed on both sides of the crack to the footings below.

However, when the wall surfaces on both sides of the crack are moving out of plane or the structure above shows stress in the form of movement or cracking sheetrock walls and ceilings above, further structural evaluation is warranted.  Foundation cracks should be sealed if periodic water infiltration occurs.  Repairing cracks from the outside if often the best method, but due to the excavation costs involved, repairing the crack from the interior by injecting a crack filling material has become a routine solution.

When horizontal wall cracks; multiple closely spaced vertical cracks; or large diagonal cracks in basement corners are observed, these conditions may indicate more serious problems related to settlement or other structural problems.  Similarly, a single vertical crack that is much wider at the top of the wall may indicated foundation settlement problems stemming from poor soil conditions; hydrostatic groundwater pressures; or frost heaving.  These problems should be directed to a knowledgeable consultant.

Regarding concrete block foundation walls, most of the guidance above can be used with some exceptions.  By their nature concrete block walls are often not well reinforced and are subject to inward movement from various soil pressures causing these types of walls can bulge inward.  Ice lens forming about 3 feet below the ground surface can expand and push concrete block walls inward.  This can even occur from a vehicle’s weight being too close to the foundation, such as oil delivery truck.  When horizontal cracking is observed in block walls, steps should be taken quickly to prevent further movement.  These types of walls are also very susceptible to water penetration even when foundation drains are present often requiring serious water proofing repairs.

The key to maintaining a sound brick or concrete block foundation is periodic vigilance to ensure loose or dislocated masonry elements are not ignored.  If you observe a ‘stair step’ patten crack in the mortar joints of a masonry foundation wall, it typically means settlement has occurred under the ‘step’ section of the wall. .  Any observed bulges or horizontal movement, as well as new cracks, should be quickly addressed.

Many Missouri condominiums have been converted from old multi-family apartment buildings with mortared or un-mortared stone foundations, some with brick foundation walls above the ground surface.  These foundations have stood the test of time and are more than 100 years old and if well maintained can last another 100 years.  They are more likely to allow the entrance of ground water due to their porous nature and the necessary steps should be taken to protect the structural elements and indoor air quality of the building if high moisture is a problem.  Old foundations are like people.  As they age, they need some extra care but they have already met the test of time.

Read more

What Are Reserve Studies & How To Select A Provider?

“Assessment increases and stronger reserve funds will be needed to repair aging properties” was the number one prediction of experts surveyed by Common Ground, the magazine of the Community Associations Institute.

The most important element of credible reserve studies is valid component data.

Recent legislation in several states also emphasizes properly funded reserves and cites reserve studies as a necessary procedure in estimating funding requirements.

Capital Reserves are for projected repairs and replacements. Items such as regular periodic (non-annual) repairs (e.g., painting), irregular periodic repairs (e.g., deck surfacing), foreseeable failure, catastrophic failure, and outdated design/aesthetics may be included in a Capital Reserve budget.

Scope of Services

The standard, or full reserve study consists of five elements. The Component Inventory is the task of selecting and quantifying Reserve Components. Condition Assessment is the task of evaluating the current condition of the components. Life and Valuation Estimating establishes the Useful Life, Remaining Useful Life, and Repair or Replacement Cost estimates for the Reserve Components. Fund Status is determined by projecting the current and future funding of the Capital Reserve Account against current and future repair and maintenance requirements. The Funding Plan is intended to create options for achieving the desired funding levels to offset anticipated expenditures.

It is critical at the outset of any project to clearly define the scope of services. Annual maintenance items are typically excluded from a reserve study. The minimum scope of service may also be defined by statutory regulation.

Standards of Reserve Studies

In 1998, the Community Associations Institute adopted National Reserve Study Standards. The standards define three levels of service (a full reserve study as defined above, an update, and an update without an on-site visit), definitions of various terms, and the contents of the report. The standards also create the professional designation Reserve Specialist. The designation is awarded by CAI to individuals with the appropriate background, experience, and references, following a review of their work by the Reserve Specialist Designation Board.

State Legislation

Prompted by foreclosures and mismanaged properties, a number of states have already passed legislation governing the management of Common Interest Realty Associations (CIRAs). Among those that have passed legislation are Alaska, California, Florida, Hawaii, Illinois, Indiana, Massachusetts, Michigan, Minnesota, Oregon, Texas, and the District of Columbia. Some states address reserve studies broadly. Others are more specific.

For example, the California Davis-Stirling Common Interest Development Act states in part: At least once every three years the board of directors shall cause a study of the reserve account requirements of the common interest development to be conducted if the current replacement value of the major components which the association is obliged to repair, restore, replace or maintain is equal to or greater than one-half of the gross budget of the association for any fiscal year.

Florida statutes are even more specific. These accounts shall include, but are not limited to, roof replacement, building painting, and pavement resurfacing, regardless of the amount of deferred maintenance expense or replacement cost, and for any other item for which the deferred maintenance expense or replacement cost exceeds $10,000. The amount to be reserved shall be computed by means of a formula which is based upon estimated life and estimated replacement cost or deferred maintenance expense of each reserve item.

How to Select a Reserve Study Consultant

The most important element of a credible reserve study is valid component data. Inaccurate cost information, improper assessment of the condition of each component, and failure to examine ways of maintaining components to prolong their useful life can lead to underfunding or, almost as problematic, overfunding of the reserve account.

Reserve studies are a professional opinion. The value of that opinion is directly related to the knowledge and expertise of the person rendering it. Always ask the consultant for references and a statement of experience and qualifications. Even this may not tell the whole story, however. Here are some other factors to consider.

  • Is the consultant locally based? Materials and their performance will vary according to regional preference and climate.
  • Does the consultant thoroughly understand building systems? Databases work only for typical systems and components, not actual ones.
  • Does the consultant have the ability to diagnose problems, design repairs, and oversee construction? A reserve study also includes an evaluation of defective components and systems in need of immediate repair.
  • Will the consultant be available for questions and follow up? Often, there is a need to explain the findings to the board or individual members.
  • Does the financial model have credibility? The model and format should be prepared by someone with an accounting background and comply with the guidelines of the American Institute of Certified Public Accountants.

The Engineering Advisor is intended to enhance your knowledge of technical issues relating to buildings. For additional information on any subject, please feel free to call us. Our commitment is to provide you with timely, accurate information.

Contact us to discuss learn more about our HOA Reserve Study services.

Read more